Detail Unit: KT 7230 GU (Progress: 100%)
Identitas Unit
Unit ID (System) 230
Plat Nomor KT 7230 GU
Product Code -
Kondisi Recondition
Spesifikasi
Model -
Tipe -
Axle -
Tahun -
Lokasi & Status
Area Saat Ini DELIVERED
Site -
Client -
Referensi
No SPK -
Purchase Code -
Karoseri -
Status Pengerjaan Komponen
Prog. Periksa Mesin (PPM) RFU
Status RFU - READY FOR USE
PIC -
Mulai - -
Selesai - 08:43:00
Durasi -
Wheel Tyre Rim (WTR) RFU
Status RFU - READY FOR USE
PIC -
Mulai - -
Selesai - 08:42:00
Durasi -
Suspension (SUS) RFU
Status RFU - READY FOR USE
PIC Didik pur
Mulai 2026-06-18 10:42:00
Selesai 2026-06-22 10:43:00
Durasi 4 Hari
Engine (Install) RFU
Status RFU - READY FOR USE
PIC -
Mulai - -
Selesai 2026-07-06 15:37:00
Durasi -
Transmission (Install) RFU
Status RFU - READY FOR USE
PIC Didik pur
Mulai 2026-06-18 01:31:00
Selesai 2026-07-06 02:32:00
Durasi 18 Hari
Axle (Install) RFU
Status RFU - READY FOR USE
PIC Didik pur
Mulai 2026-06-18 15:32:00
Selesai 2026-07-06 15:32:00
Durasi 18 Hari
Electrical (ELC) RFU
Status RFU - READY FOR USE
PIC rio
Mulai 2026-07-17 09:27:00
Selesai 2026-07-20 09:03:00
Durasi 2 Hari 7 Jam
Air Conditioner (ACD) RFU
Status RFU - READY FOR USE
PIC ridwan
Mulai 2026-07-15 10:03:00
Selesai 2026-07-17 09:27:00
Durasi 1 Hari 7 Jam
Main Frame Chasis (MFC) RFU
Status RFU - READY FOR USE
PIC -
Mulai - -
Selesai - 08:43:00
Durasi -
Accessories (ACC) RFU
Status RFU - READY FOR USE
PIC Gosong
Mulai 2026-07-09 14:39:00
Selesai 2026-07-17 09:27:00
Durasi 7 Hari 2 Jam
Final Check (FNC) RFU
Status RFU - READY FOR USE
PIC beni
Mulai 2026-07-17 09:27:00
Selesai 2026-07-24 18:43:00
Durasi 7 Hari 6 Jam
Painting (PNT) RFU
Status RFU - READY FOR USE
PIC rijal
Mulai 2026-07-24 14:43:00
Selesai 2026-07-24 18:15:00
Durasi 1 Jam
REBUILD - Engine RFU
Status RFU - READY FOR USE
PIC -
Mulai 2026-06-22 09:00:00
Selesai 2026-07-04 15:00:00
Durasi 12 Hari 6 Jam
REBUILD - Transmission RFU
Status RFU - READY FOR USE
PIC -
Mulai 2026-07-01 08:30:00
Selesai 2026-07-04 15:00:00
Durasi 3 Hari 6 Jam
REBUILD - Axle RFU
Status RFU - READY FOR USE
PIC -
Mulai 2026-06-30 08:30:00
Selesai 2026-07-03 15:00:00
Durasi 3 Hari 6 Jam